Bathroom Refurb, Woosehill
For this project, we’re stripping out the current bathroom and replacing with new tiles and sanitary ware. This includes replacing the existing shower tray and moving it to the opposite end of the room where the bath was and adding an 1800cm shower tray.
Updates
StartedOld bathroom, ready to be stripped of the sanitary ware and tiles.
May 2026
StartedNote the position of the old shower tray. The bathroom will have a completely new layout.
May 2026
In progressTiles fully stripped off and the existing bath removed. The new shower tray has been bedded before we make the walls good, ready for tiling.
May 2026
In progressFeature wall in the shower is now fitted. We use the orange levelling clips to ensure the tiles remain in place whilst the adhesive dries and keeps the tiles flat.
May 2026
In progressWe've just finished tiling this shower enclosure with a nice polished slate-effect finish – the random brick pattern gives it a modern look while the large format tiles keep it clean and easy to maintain.
May 2026
FinishedThis is the finished shower enclosure with full rainfall head and hand shower setup. We've tiled the walls with ceramic slate-effect tiles and fitted a frameless glass screen with chrome fixings to give a clean, modern look that's easy to maintain.
June 2026
FinishedThis bathroom's nearly finished – we've installed the vanity unit with basin, fitted the mirror and lighting, and got the tiling complete. Just a few final touches to go before handover.
June 2026
FinishedWe're just applying the final touches and last up is the lighted mirror behind the sink. That’s a wrap of this bathroom refurb!
June 2026